2005 SPLOST Project Name Project Number Project Status
 last updated March 2013    
D4010
Under construction
Cedarcrest Road Widening D4070 In design
Cobb Parkway - Bridge over Chattahoochee River
GDOT Project
In design
TR295
Under construction
I-285 at Atlanta Road Interchange D4100 In design
I-75 at Third Army Road Interchange D4260 In design
D4120/D6120
Under construction
D4130C
Under construction
GDOT Project
In design
D6140
Under construction
Noonday Creek Trail D11D0/ D11E0 Under construction
D6200
In design
 Sope Creek Bridge Replacement  D1300 In design
 2011 SPLOST Concept Layout  Project Number  
     
 Concept Layout - Pine Mountain Road
City of Kennesaw
16.56MB
 E6030  2011 SPLOST Website
 Concept Layout - Pine Mountain Road
Cobb County
11.32 MB
 E6030




Project Name: Barrett Parkway Thoroughfare Improvements (US41 to Dallas Highway)

Project No.:
D4010

Commission District:
District 1

Last Web Update:
November 2012

Project Description:
This project consists of 3.58 miles, exclusive of side streets, of widening from 4-lane divided roadway to 6-lane divided roadway from approximately 1800 feet south of Burnt Hickory Road to the intersection of Barrett Parkway and Cobb Parkway (US41); includes widening of the existing bridge over Noonday Creek and a 10-ft asphalt multi-use trail; and includes installation and modification of traffic signals and ATMS system.

Project Schedule:
This project is scheduled for completion by summer 2013.

Project Manager Information:
For additional information on this project, please contact the project manager This e-mail address is being protected from spambots. You need JavaScript enabled to view it at 770-528-4375.


Project Downloads:

Handout pdf icon

Barrett Parkway at Burnt Hickory BOC Approved Concept pdf icon

Concept Map 1 - Barrett Parkway South End pdf icon

Concept Map 2 - Barrett Parkway North End pdf icon






Project Name:
Cedarcrest Road Widening - Cobb and Paulding Counties

Project No.:
D4070

Commission District:
Districts 1 

Last Web Update:
February 2012

Project Description:
Cedarcrest Road is a two-lane roadway that runs approximately 6.27 miles between US 41/Cobb Parkway Northwest in Cobb County and the Dallas Acworth Highway intersection with Hiram Acworth Highway at the Cross Roads community of Paulding County. The proposed undertaking would widen and improve Cedarcrest Road from Harmony Grove Church Road to Governors Towne Drive. These improvements would be made through two projects—one to be completed by Paulding County’s Department of Transportation utilizing local funding and the other to be constructed by Cobb County’s Department of Transportation utilizing a combination of local funding and federal highway funds.

Project Schedule:
This project is currently in design.

Project Manager Information:
For more information about this project, please contact Cobb DOT Engineering, Scott Jordan, Project Engineer at 770-528-3685.

Project Downloads:

Cedarcrest Fact Sheet alt

Cedarcrest Road Map - Cobb County alt

Cedarcrest Road Map - Paulding County south 1 alt

Cedarcrest Road Map - Paulding County north 2 alt




 



Project Name: Cobb Parkway - Bridge Replacement over Chattahoochee River - GDOT Project

Project No.:
D11E0

Commission District:
District 2

Last Web Update:
February 8, 2011

Project Description:
This project includes replacing the bridge over the Chattahoochee River located in Cobb and Fulton Counties, Georgia. To accelerate construction of the new bridge, this project has been split into two phases:

Phase 1: From Northgate Drive to Paces Mill Road. This phase will include reconstruction and widening of the bridge over the Chattahoochee River.
The length of this proposed phase is 0.53 miles.

Phase 2: From Mount Paran Road to Northgate Drive. This will widen the existing roadway from 4-lanes to 6-lanes between Mount Paran Road and Northgate Drive.

Project Schedule:
Right-of-way acquisition authorization awaiting final environmental approval, final plans being completed, letting currently scheduled for March 2011.

Project Manager Information:
For more information, please contact Cobb DOT Engineering, This e-mail address is being protected from spambots. You need JavaScript enabled to view it , Project Engineer at 770-420-6659

Project Downloads:

Click here to view Phase 1 PDF alt

Click here to view Phase 2 PDF alt

Click here for GDOT Project Handout alt






Project Name: Floyd Road Widening

Project No.:
D11E0

Commission District:
District 4

Last Web Update:
 June 2012

Project Description: 
Floyd Road is being designed as a 4 lane-divided road way with a 20 feet raised median, from Clay Rd to Hicks Rd. The median will be landscaped and a 10 feet wide enhanced sidewalk will be added on the west side of Floyd Road with a 5 feet grass strip. A 5 feet sidewalk will be added on the east side.

A concept plan has been approved by Georgia Department of Transportation [GDOT]and environmental approval by GDOT is awaited. After that, a public information open house will be held to invite comments from citizens [Spring 2009].

Project Schedule:
This project is currently in design. Right-of-way acquisition started Fall 2009 and construction is expected to begin in early 2012.

Project Manager Information:
For more information, please call This e-mail address is being protected from spambots. You need JavaScript enabled to view it at 770-420-6658
.

Project Downloads:

Click here to view the Floyd Road Corridor concept map alt 6.35 MB updated May 6, 2009

Click here to view the Fact Sheet alt

A Groundbreaking Event was held Thursday, June 21, 2012. Click here for more informationalt






Project Name: I-285 at Atlanta Road Interchange Improvements

CCDOT Project No.:
D4100

GDOT Project No.: PI 752300

Federal Project No.: STP00-0222-01(001)

Commission District:
District 2

Last Web Update:
August 2012

Project Description:
Modify the interchange at Atlanta Road and I-285 by replacing the existing bridge structures and adding left turn lanes along Atlanta Road to access both NB & SB traffic onto I-285; add aux. lanes along I-285 from Atlanta Rd to Paces Ferry Rd interchange and replace Orchard Rd Bridge over I-285.

Project Schedule:


Preliminary Field Plan Review: February 2011

R/W Acquisition: Notice to proceed May 2012

Let Date: March 2014

Project Manager Information:

For more information please contact This e-mail address is being protected from spambots. You need JavaScript enabled to view it Project Engineer at 770-528-4361.

Project Downloads:

Concept Plan as of October 15, 2011 alt

Public Meeting Handout alt




alt


Project Name: I-75 at Third Army Road Interchange

Project Numbers:
D4260

Commission District:
District 1

Last Web Update: April 2013

Project Description: 
The purpose of this project is to provide safety and operational improvements, and reduce traffic congestion on those roads that feed traffic from northern Paulding County, Southern Bartow County and northwest Cobb County to and from I-75.  Currently, commuters use US 41 and SR 92 predominately to gain access to the interstate system. SR 92 crosses Lake Allatoona and goes through historic Acworth.  It would be difficult to widen SR 92 to accommodate this traffic.  Due to congestion along these corridors, commuters are taking alternative routes to gain access to the interstate including perceived short cuts through communities.  This has created safety and operations issues as well as congestion on facilities that were not designed to accommodate this degree of traffic.

 

The Third Army Road project will address these issues by creating a access controlled roadway between US 41 and a new interchange on I-75 that basically follows the existing Third Army Road, hence the name of the project.  This new facility will provide direct access to the area as described above with the new interchange on I-75. A grade separated interchange with US 41 is also being considered to further alleviate potential congestion on US 41.


Project Schedule:
Currently, only the scoping phase is underway with a duration of approximately 18 months.  The deliverables of this phase consists of an approved Environmental document and approved concept.  Upon completion of this Phase, construction plans will be prepared and the project let to construction.  If funding is located, it is anticipated that construction will begin by 2017 and will take two years to complete construction.

Project Manager Information: For additional information on this project, please contact the project manager Mike Cates at 770-420-6659. Comments on the project will be accepted until April 11, 2013 and can be sent to the attention of This e-mail address is being protected from spambots. You need JavaScript enabled to view it .


Project Downloads:

alt
alt Project Illustration

alt Before and After
Illustration

alt Alternate A

alt Alternate B

alt Alternates A & B

alt AM Trip Times

alt PM Trip Times
 

 

 

alt March 28, 2013 Meeting Handout
 





 


 


Project Name: Jamerson Road/Wigley Road/Kell High School Roadway Improvements

Project No.:
D6120

Commission District:
District 3

Last Web Update:
August 2012

Project Description: 
The project consists of various improvements for the Jamerson Road – Jamerson Road/Wigley Road area. Jamerson Road will be widened from a 2-lane to a 4-lane divided road from Lee Waters Road to Canton Road. Jamerson Road/Wigley Road will be widened from 2 lanes to 3-lanes from Sandy Plains Road to Lee Waters Road.

The four-lane roadway will transition to a three-lane roadway with right turn lanes at intersections. Kell High School improvements include extension of turn lanes along Lee Waters Road. This project also includes the construction of six retaining walls.

Project Schedule:
This project is currently under construction with expected completion November 2012.

Project Manager Information:
For more information, please contact This e-mail address is being protected from spambots. You need JavaScript enabled to view it , Project Engineer, at 770-528-4361.

Project Downloads:(BOC-approved concept 06/10/ 2008)

Concept Layout 1
 alt , Concept Layout 2 alt






Project Name: Jiles Road, Thoroughfare Improvements (Phase III)

Project No.:
D4130 A

Commission District:
District 1

Last Web Update: November 2012


Project Description:
This project, broken into 3 phases, will increase the existing capacity and improve operational deficiencies that will provide for better traffic flow on Jiles Road.
Phase I includes roadway between Baker Road and Cherokee Street and includes widening to 4 lanes in each direction with a raised median. This project is complete.

Jiles Road Phase II will include a new bridge (parallel to the existing one) over the railroad to add additional capacity (between Baker Road and moon Station Road). This project is complete.

Phase III will have improvements between US 41 and the CSX bridge.

Project Schedule:
Phase 1 complete, Phase II complete, Phase III is scheduled to be complete Summer 2013.

Project Manager Information:
For more information, please contact This e-mail address is being protected from spambots. You need JavaScript enabled to view it , Project Engineer, at 770-528-4375.

Project Downloads:

Public Meeting Handout alt

Concept Sheet 1of 4 alt

Concept Sheet 2 of 4 alt

Concept Sheet 3 of 4 alt

Concept Sheet 4 of 4 alt




Lake Acworth Drive/ SR 92 - GDOT Project

GDOT held a Location and Design Public Information Open House on July 8, 2008 for the proposal to widen SR 92 from two to four lanes between US 41 and Cowan Road at I-75. Click here for more info alt





Project Name: Lower Roswell Road (East)

Project No.:
6140

Commission District:
District 2

Last Web Update:
August 2012

Project Description:
Safety and operational improvements to Lower Roswell Road from Davidson Road to Timber Ridge Road through the addition of turning lanes, bicycle lanes, sidewalk and a multi-use trail.

This project consists of the addition of sidewalks, trail, and bike lanes along a 2.9 mile portion of Lower Roswell Road, from Davidson Road to Timber Ridge Road. A roundabout is included at the end of the project, where Lower Roswell Road intersects with Willeo Road and Timber Ridge Road.

Project Schedule:


Phase 1: Davidson Road to Waterford Green/start of National Park
Start construction October 2011, substantially complete by December 2012

Phase 2:  Waterford Green/start of National Park to Timber Ridge Road/Fulton County line
Start construction July 30, 2012.  Completion is anticipated for the entire project by December 2013.

Project Manager Information: For more information please contact This e-mail address is being protected from spambots. You need JavaScript enabled to view it Project Engineer at 770-528-4361.

Project Downloads:

Please note: Concept files alt are very large files; download times will vary.

Revised concepts as of October 20, 2008:

map 1 of 5 (Asheforde Dr. to Heyward Sq.)

map 2 of 5 (Davidson Rd. to Sunset Trail)

map 3 of 5 (Heyward Sq. to Hyde Road)

map 4 of 5 (Hyde Road to Richmond Hill)

map 5 of 5 (Roundabout at Timber Ridge)

Fact Sheet alt

Project Website: Lower Roswell Road (East)- Project No. 6140






Project Name: Noonday Creek Trail, Multi-Use Trails

Project No.:
D11D0

Commission District:
District 1

Last Web Update:
March 2012

Project Description: 
The Noonday Creek Trail is a culmination of efforts between the Town Center Area Community Improvement District (TCACID), Cobb County, and the National Park Service. This trail will connect to the existing Kennesaw Mountain National Battlefield Park trail system and the proposed West Cobb Trail, planned to be constructed adjacent to Barrett Parkway between Dallas Highway/SR 120 and Cobb Parkway/US 41.

The proposed trail will run from the National Park on Old Highway 41 to Barrett Parkway, will join the West Cobb Trail along Barrett Parkway, run down Cobb Parkway to Vaughan Road and run down portions of Vaughan Road and Cobb Place Boulevard to Barrett Lakes Boulevard. The trail will run down Barrett Lakes Boulevard to Noonday Creek, and then follow Noonday Creek to Bells Ferry Road.

Additional plans are in place to add trailheads and parking throughout the trail corridor. Future phases of the trail will also connect to Noonday Park and points northward toward and into Cherokee county.

Sections of the trail currently under construction are north of Barrett Parkway and east of Cobb Parkway. Additional construction projects will be added over the next couple of years.

Project Schedule: 
Work continues on the nearly 7-mile-long Noonday Creek Trail which will connect pedestrians and cyclists from the Town Center mall area to Kennesaw Mountain National Battlefield Park. The goal of this project is to link residential areas with commercial and industrial areas, and to make these areas much more accessible to pedestrians and cyclists.

Phase 1A: Complete

This completed project is along the south side of Old 41 Highway from the intersection with Stilesboro Road to the northern boundary of the National Park System.  Also included in this project was a 279 space parking lot at the CSX Railroad site purchased by Cobb County.  

Phase 1B:  Under Construction
Construction for this phase of the project is anticipated to begin in Fall 2011 with expected completion in Summer 2012.  This project includes the placement of curb and gutter along the northern side of the road within the National Park Service park boundary (opposite the trail side) and resurfacing the Old 41 Highway within the park.  This project also contains the extension of the trail along the southern side of Old 41 Highway from the park northern boundary to a match point just south of Barrett Parkway.  From this match point, the trail will be built as a part of the Barrett Parkway widening project, scheduled to advertise later this year. 

Phase 2A: Complete
The placement of trail for this phase is along Cobb Parkway (US 41) from Barrett Parkway northward to Noonday Creek which is about 0.33 mile.  The trail starts on the western side of Cobb Parkway swapping sides to the eastern side at the signalized intersection with Vaughn Road.  Construction is underway with an completion in early 2011.

Phase 2B: Complete
In early September, the Cobb County Board of Commissioners and members of the Town Center Area Community Improvement District celebrated the completion of this phase of the trail with a ribboncutting ceremony. This section begins at Cobb Parkway(US 41) and runs along Noonday Creek, Vaughn Road, back along the creek, then back along Vaughn Road, Cobb Place Blvd., Barrett Lakes Blvd. to the intersection with Duncan Road and includes a scenic pedestrian bridge over Noonday Creek. 

Phase 2C: Under Construction
This phase continues from Phase 2B and runs northward along Barrett Lakes Blvd. to Noonday Creek.  Then the trail runs along Noonday Creek and under I-75, crosses Busbee Parkway at Town Center Drive, under I-575 and Chastain Meadows Parkway before ending at the western side of Bells Ferry Road.  A small gravel parking lot on county owned land just off of Bells Ferry Road will be proposed as a trail head.  Coordination with many agencies, including the Federal Highway Administration, was a necessary part of the planning stages from this project as it involved the careful consideration of 4 creek bridges and impacts to numerous sections of wetlands and stream buffers. This phase of the project is scheduled to begin construction in late spring 2012.  

Project Manager Information:
For more information, please contact Noonday Creek Trail project manager This e-mail address is being protected from spambots. You need JavaScript enabled to view it at 770-420-6664.

Project Downloads:

 

alt


Constructed in five phases, the paved trail will be 8 to 10 feet wide and have a dotted line to separate pedestrians and cyclists. SPLOST Funding for this project was supplemented with funds from the Town Center Area Community Improvement District, National Park Service and the Georgia Department of Transportation


Click here to view a map of project phase locations.


 




Project Name:
Queen Mill Road

Project No.:
D6200

Commission District:
District 4

Last Web Update:
February 8, 2011

Project Description:
This project consists of safety and operational improvements to Queen Mill Road from Mableton Pkwy. to Veterans Memorial Hwy. The 1.8 mile project limit includes curb, gutter, sidewalk, drainage design, and geometric improvements where needed.

Project Schedule:
This project is currently in design.

Project Downloads:

alt Concept Design 1

alt Concept Design 2

alt Handout



Project Name: Paper Mill Road Bridge Replacement over Sope Creek

Project No.: D1300

Commission District: District 1

Last Web Update: February 2013

Project Description: This project consists of the total replacement of the existing Paper Mill Road bridge over Sope Creek. Paper Mill Road will be closed to all traffic for approximately 3 months while the existing bridge is removed and the new replacement bridge constructed. Paper Mill Road will be reopened to traffic after substantial completion has occurred. Substantial completion consists of the bridge completed to the point of accepting traffic and the approach roadways completed except for the final surface layer. Work remaining may consists of final grading, grassing, sidewalks, guardrails, permanent signing and pavement markings and final adjustments of any temporary relocated utilities. All work should be started and completed within 4 months.

Project Schedule: Project begins construction in May 2013; close the road to all traffic, May 28; road closed for approximately 3 months; total construction period 4 months with expected completion by October 2013. Dates are subject to change as final plans are developed.

Project Manager Information: For more information, please contact James Hudgins at This e-mail address is being protected from spambots. You need JavaScript enabled to view it   or 770-420-6658.